Release engineering
|
||
|
===================
|
||
|
|
||
|
To forge a successful stable release of the Haiku operating system, several important tasks must be accomplished. These steps are time tested as a best roadmap to draft a successful release of Haiku.
|
||
|
|
||
|
Important first steps
|
||
|
---------------------
|
||
|
|
||
|
* Review blockers for the next release in [Trac](https://dev.haiku-os.org)
|
||
|
* A minimum of 25% of the individuals in the [contributors group](https://review.haiku-os.org/admin/groups/23fa29f291e2dd5d41452202147d038f020fc8db,members) should reach concensus of the need for a stable release
|
||
|
* Over time this may change to a time-based stable release schedule.
|
||
|
* Community nomination of a Release Coordinator
|
||
|
* Should be someone from the contributors group
|
||
|
* Should have visibility of most aspects of Haiku
|
||
|
* Should have good coordination and communication skills
|
||
|
* Generally occurs via the mailing list haiku-development
|
||
|
* Timeline proposals are proposed via the haiku-development mailing list
|
||
|
|
||
|
Forming a timeline
|
||
|
------------------
|
||
|
|
||
|
An important aspect of drafting a release is forming a timeline. The Release Coordinator's role is to drive Haiku towards this release date.
|
||
|
|
||
|
* Final date for enhancements in (RELEASE)
|
||
|
* Branch buildtools for (RELEASE)
|
||
|
* Branch haiku for (RELEASE)
|
||
|
* Setup CI/CD pipelines for (RELEASE)
|
||
|
* Generate first test candidates (TC0, TC1, etc), encourage extreme testing.
|
||
|
* Begin accepting bugfixes in branches via code review
|
||
|
* Final translations synchronization
|
||
|
* Generate first release candidates (RC0, RC1, etc), encourage testing.
|
||
|
* Profit
|
||
|
|
||
|
* R1/Beta 2's timeline from branch to release was roughly 35 days
|
||
|
* R1/Beta 3's timeline from branch to release was roughly 50 days.
|
||
|
|
||
|
Release dates can slide, it's ok.
|
||
|
We just try to slide pragmatically (+1 week because of X,Y,Z)
|
||
|
|
||
|